Only 86 out of 414 dams have been repaired

Only 86 out of 414 dams have been repaired
Only 86 out of 414 dams have been repaired

BGN 500 million for the repair of the dams was allocated in 2018.

Only 86 out of 414 are repairthe Iranians damand which had to be repaired by the state company “Montazhi” and for which BGN 500 million was allocated in 2018, informs 24 HOURS.

This is according to a report on the progress of the activities as of the beginning of September, published on the page of “Mountains”. Within a month – from the beginning of August, one was completed dam. As of the first of July repairIranians were 76, and as of June 1 – 68.

The latest report shows that 8 damand are on the final right and have a degree of completion of constructionit over 90%. However, it reflects the progress of repairbut the restoration works for 267 dama, because only they are assigned for implementation by the State Consolidation Company to its subsidiary “Montazhi”. This was recorded as of April 18 this year, meaning that the DCC has not commissioned since then repairand.

Of these 267 damand at 140 they are not started at all repairour activities, but are at the design stage.

It is also striking that quite a few of damare out of contract – either on January 15 or on March 16, 2021.

A year ago Kiril Petkovwho was on duty at the time Minister of Economyrevealed that the completed damand there are only 10, and they did not even have a building permit and are illegal. Furthermore constructionit was done at inflated prices – 5 times for the transport and 2 times for the concrete.

Some unit prices are published on the “Montazhi” website – for example, for a concrete pump, the amount is BGN 195 without VAT for a machine change. The invoices for all concluded contracts for the purchase of concrete mixes have also been uploaded. It is clear from them that the prices per cubic meter vary between BGN 70 and BGN 105, with the most common amount being BGN 95.

The state-owned company received the financing of BGN 500 million through an in-house procedure – that is, without a competition, but with a direct award. And then through contracts for the supply of materials and equipment rental, in fact repairthey were transferred to private companies. It is noteworthy that many of them are contracted with the same companies.

In order to solve the problem of illegal constructions, the current minister of regional development, Ivan Shishkov, proposed for public discussion an amendment to the Law on Territorial Planning (ZUT) to legalize them. This will apply not only to dambut also for the already built elements on the new lots of the “Hemus” highway, for which there were also no construction documents issued.

Two weeks ago, Shishkov commented that attempts were made to cover up the illegals repairand on damand. “In February of this year, a commission was formed by the Ministry of Regional Development and the Ministry of Economy and Industry, which issued a decision that repairare emergency and there was no need to issue building permits for repairthe. There is also an interpretive letter to all the chief architects of the municipalities to issue building permits for emergency works repairand on damthe. This is disturbing”Shishkov told then.

In February of last year, the Parliament commissioned the Audit Chamber to conduct an audit of “Montazhi” in connection with repairand on the 414s dama. The audit was sent to prosecutors this year, but has since been classified pending the conclusion of possible criminal proceedings.


The article is in bulgaria

Tags: dams repaired